Mmmm bit confused , woodseats road is shut today and till 9am tomroow was expecting the bridge work to be done but they appear to be doing utility works at the bottom and the barriers etc are still there and there is no one working on the bridge its self

 

Just looked on council website todays closeure isnt mentioned however it states that the road will be resurfaced on the weekend of the 24th - YIPPPEEE

Edited by bus man

Share this post


Link to post
Share on other sites

Have noticed over the last few weeks they seem to have been completing the south side of the bridge and the kerb and pavement. There were large holes that were filled in the adjoining subsoil. They then moved the temporary barriers over so they could work on the north side of the bridge.

Presumably this will take longer as the cables and pipes are over this side.

Share this post


Link to post
Share on other sites

Yep, I went over it when it opened at just after 3am. Finally no more traffic lights

Share this post


Link to post
Share on other sites
Yep, I went over it when it opened at just after 3am. Finally no more traffic lights
There are two new looking lights on the Post Office side but none on the Abbeydale Road side, aren't they going to take them down?

Share this post


Link to post
Share on other sites

Several threads on this long-running saga (still running!) have been merged here.

Edited by Jeffrey Shaw

Share this post


Link to post
Share on other sites
There are two new looking lights on the Post Office side but none on the Abbeydale Road side, aren't they going to take them down?

 

I think they are still there because there was a patch of tarmac that was not finished last night. I suppose that this is so cyclists and motorcyclists can see that there is a big step in the road surface. The rest is a smooth as glass.

Share this post


Link to post
Share on other sites

I know there have been threads on S.F re this subject but can anyone please let me know if that awful galvanised steel monstrosity is the finished product or a temporary arrangement until a magnificent piece of contemporary architectural civil engineering is finally erected.

Share this post


Link to post
Share on other sites

I agree , I thought they were going to paint it, but so far they haven't. There was a picture of how it was going to look. I am sure the picture showed a green bridge.

Share this post


Link to post
Share on other sites

They are probably waiting for a dry spell to paint it. Might be waiting a long time then!

Share this post


Link to post
Share on other sites

Paint adheres to galvanized steel better if it's allowed to weather for a few months first.

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.